Image Galleries
Late August, 2005
These photos show progress on the new biomass processing facility at OGS during late August, 2005.
Early August, 2005
These photos show progress on the new biomass processing facility at OGS during early August, 2005.
May-June, 2005
These photos show progress on the new biomass processing facility at OGS during May and June of 2005.
Twin Bale Conveyor
Bales are loaded onto the twin bale conveyor with a four bale grapple attached to a teleboom loader. This 'double wide' design provided a shorter conveyor that could hold up to 12 bales. A single line conveyor that could hold this many bales would extend farther than the building allowed. Allowing 12 bales of capacity only required loading once an hour.
Bale Merge Conveyor
The merge conveyor is a 'double wide' conveyor as well. This conveyor accepts bales from the twin bale conveyor and swings from side to side to load bales one at a time onto the single processing line.